[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103790":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103790,780,1,"单选题","工程监理单位调换总监理工程师，应征得()书面同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","总承包单位",false,{"key":20,"text":21,"correct":18},"C","质量监督机构",{"key":23,"text":24,"correct":18},"D","建设行政主管部门","2020版教材P94-97 工程监理单位调换总监理工程师，应征得建设单位书面同意。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]