[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103788":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103788,780,1,"单选题","下列选项中，工程建设强度涵含的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程结构所能承受的强度",false,{"key":16,"text":17,"correct":14},"B","政府对工程建设管理的力度",{"key":19,"text":20,"correct":21},"C","单位时间内投入的工程建设资金的数量",true,{"key":23,"text":24,"correct":14},"D","单位时间内投入的工程建设人员的数量","2020版教材P102-106 工程建设强度是指单位时间内投入的建设工程资金的数量，工程建设强度=投资／工期。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]