[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103748":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103748,780,1,"单选题","(2016年真题）下列工程目标控制任务中，不属于工程质量控制任务的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","审查施工组织设计及专项施工方案",false,{"key":16,"text":17,"correct":14},"B","审查工程中使用的新技术、新工艺",{"key":19,"text":20,"correct":21},"C","分析比较实际完成工程量与计划工程量",true,{"key":23,"text":24,"correct":14},"D","复核施工控制测量成果及保护措施","本题考查的是监理规划主要内容。选项C属于工程造价控制工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]