[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103732,780,1,"单选题","(2011年真题）根据《建设工程监理规范》，监理规划应在（ ）后开始编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","收到设计文件和施工组织设计",false,{"key":16,"text":17,"correct":14},"B","签订委托监理合同及收到设计文件和施工组织设计",{"key":19,"text":20,"correct":14},"C","签订委托监理合同及收到施工组织设计",{"key":22,"text":23,"correct":24},"D","签订委托监理合同及收到设计文件",true,"监理规划应在签订建设工程监理合同及收到工程设计文件后由总监理工程师组织编写，并应在召开第一次工地会议7天前报建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]