[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103728":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103728,780,1,"单选题","(2012年真题）下列监理工作措施中，属于进度控制技术措施的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完善职责分工及有关制度",false,{"key":16,"text":17,"correct":14},"B","确保资金的及时供应",{"key":19,"text":20,"correct":21},"C","建立多级网络计划体系",true,{"key":23,"text":24,"correct":14},"D","对工期提前者实施奖励","本题考核进度控制的技术措施内容。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]