[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103726,780,1,"单选题","(2014年真题）监理实施细则需经（ ）审批后实施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总监理工程师代表",false,{"key":16,"text":17,"correct":14},"B","工程监理单位技术负责人",{"key":19,"text":20,"correct":21},"C","总监理工程师",true,{"key":23,"text":24,"correct":14},"D","相应专业监理工程师","监理实施细则可随工程进展编制，但必须在相应工程施工前完成，并经总监理工程师审批后实施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]