[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103703":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103703,780,1,"单选题","下列监理工作措施中，属于进度控制技术措施的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完善职责分工及有关制度",false,{"key":16,"text":17,"correct":14},"B","确保资金的及时供应",{"key":19,"text":20,"correct":21},"C","建立多级网络计划体系",true,{"key":23,"text":24,"correct":14},"D","正确处理工程索赔事宜","2020版教材P109-122 工程进度控制具体措施包括： ①组织措施：落实进度控制的责任，建立进度控制协调制度； ②技术措施：建立多级网络计划体系，监控施工单位的实施作业计划； ③经济措施：对工期提前者实行奖励；对应急工程实行较高的计件单价；确保资金的及时供应等； ④合同措施：按合同要求及时协调有关各方的进度，以确保建设工程的形象进度。 根据第②点可知，选项C符合题意。因此，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]