[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103695":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103695,780,1,"单选题","根据《建设工程监理规范》，监理规划应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","在签订委托监理合同后开始编制，并应在召开第一次工地会议前报送建设单位",false,{"key":16,"text":17,"correct":14},"B","在签订委托监理合同后开始编制，并应在工程开工前报送建设单位",{"key":19,"text":20,"correct":21},"C","在签订委托监理合同及收到设计文件后开始编制，并应在召开第一次工地会议前报送建设单位",true,{"key":23,"text":24,"correct":14},"D","在签订委托监理合同及收到设计文件后开始编制，并应在工程开工前报送建设单位","2020版教材P122-123 依据《建设工程监理规范》GB\u002FT 50319-2013 ，监理规划应在签订建设工程监理合同及收到工程设计文件后编制，在召开第一次工地会议前报送建设单位。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]