[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103686":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103686,780,1,"单选题","下列选项中，属于工程进度控制经济措施的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","严格质量检查和验收，不符合合同规定质量要求的，拒付工程款",false,{"key":16,"text":17,"correct":14},"B","及时进行计划费用与实际费用的分析比较",{"key":19,"text":20,"correct":14},"C","按合同支付工程质量补偿金或奖金",{"key":22,"text":23,"correct":24},"D","确保资金的及时供应",true,"2020教材P109-122 工程进度控制的经济措施：对工期提前者实行奖励；对应急工程实行较高的计件单价；确保资金的及时供应等",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]