[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103684":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103684,780,1,"单选题","下列选项中，属于工程进度动态比较内容的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程进度目标值的预测分析",true,{"key":16,"text":17,"correct":18},"B","工程预算值与概算值的比较",false,{"key":20,"text":21,"correct":18},"C","工程合同价与工程预算值的比较",{"key":23,"text":24,"correct":18},"D","工程进度目标分解值与合同价比较","2020教材P109-122 工程进度动态比较的内容包括: 1) 工程进度目标分解值与进度实际值的比较; 2) 工程进度目标值的预测分析。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]