[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103680":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103680,780,1,"单选题","监理工作方法及措施中，根据措施实施时间不同，可将监理工作措施分为()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事前控制、事中控制、事后控制",true,{"key":16,"text":17,"correct":18},"B","前馈控制、反馈控制",false,{"key":20,"text":21,"correct":18},"C","开环控制、闭环控制",{"key":23,"text":24,"correct":18},"D","主动控制、被动控制","2020教材P125-129 制定监理工作措施通常有两种方式： (1)根据措施实施内容不同，可将监理工作措施分为技术措施、经济措施、组织措施和合同措施。 (2)根据措施实施时间不同，可将监理工作措施分为事前控制措施、事中控制措施及事后控制措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]