[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103669":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103669,780,1,"单选题","下列选项中，属于工程进度控制技术措施的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","完善职责分工",false,{"key":16,"text":17,"correct":14},"B","协助完善质量保证体系",{"key":19,"text":20,"correct":14},"C","对工期提前者实行奖励",{"key":22,"text":23,"correct":24},"D","建立多级网络计划体系",true,"2020教材P109-122 工程进度控制的技术措施：建立多级网络计划体系，监控施工单位的实施作业计划。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]