[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103651":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103651,780,1,"单选题","根据《建设工程监理规范》(GBT 50319-2013)，不属于监理实施细则编写依据的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","已批准的监理规划",false,{"key":16,"text":17,"correct":14},"B","施工组织设计，专项施工方案",{"key":19,"text":20,"correct":21},"C","工程外部环境调查资料",true,{"key":23,"text":24,"correct":14},"D","与专业工程相关的资料文件和技术资料","《建设工程监理规范》规定了监理实施细则编写的依据： ⑴监理规划； ⑵工程建设标准、工程设计文件和技术资料； ⑶施工组织设计、(专项)施工方案。 还可以融入工程监理单位的规章制度和经认证发布的质量体系。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]