[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103650":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103650,780,1,"单选题","下列关于为完成施工阶段质量控制任务，项目监理机构需要做好工作的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审查确认施工总包单位及设计单位资格",true,{"key":16,"text":17,"correct":18},"B","检查施工机械和机具质量",false,{"key":20,"text":21,"correct":18},"C","检查工程材料、构配件、设备质量",{"key":23,"text":24,"correct":18},"D","协助建设单位做好施工现场准备工作，为施工单位提交合格的施工现场","本题考查的是监理规划主要内容。选项A错误，属于招投标阶段及设计阶段的内容。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]