[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103622,780,1,"单选题","根据《建设工程监理规范》GB／T 50319—2013，监理规划的编制时间为()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","接到监理中标通知书及签订建设工程监理合同后",false,{"key":16,"text":17,"correct":14},"B","签订建设工程监理合同及收到施工组织设计文件后",{"key":19,"text":20,"correct":14},"C","接到监理投标邀请书及递交监理投标文件前",{"key":22,"text":23,"correct":24},"D","签订建设工程监理合同及收到设计文件后",true,"2020教材P107-109 监理规划应在签订建设工程监理合同及收到工程设计文件后由总监理工程师组织编制，并应在召开第一次工地会议 7 天前报建设单位。监理规划报送前还应由监理单位技术负责人审核签字。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]