[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103608,780,1,"单选题","(2018年真题）下列工程进度控制任务中，属于项目监理机构在施工阶段进度控制的任务是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","编制工程建设总进度计划",false,{"key":16,"text":17,"correct":14},"B","依据进度控制纲要确定合同工期",{"key":19,"text":20,"correct":14},"C","进行工程项目建设目标论证",{"key":22,"text":23,"correct":24},"D","审查施工单位提交的进度计划",true,"本题考查的是目标控制。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]