[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103599":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103599,780,1,"单选题","(2016年真题）下列建设工程目标动态控制工作中，属于PDCA中检查工作的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","编制工程项目计划",false,{"key":16,"text":17,"correct":14},"B","实施工程项目计划",{"key":19,"text":20,"correct":21},"C","收集工程项目实施绩效",true,{"key":23,"text":24,"correct":14},"D","采取偏差纠正措施","本题考查的是目标控制。选项A属于计划的工作，选项B属于执行的工作，选项D属于纠偏的工作。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]