[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103595,780,1,"单选题","(2016年真题）关于建设工程质量、进度和造价三大目标的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应形成“自上而下层层展开、自上而下层层保证”的质量、进度和造价目标体系",false,{"key":16,"text":17,"correct":18},"B","应将建设工程总目标分解，为质量、进度和造价目标动态控制奠定基础",true,{"key":20,"text":21,"correct":14},"C","在不同的建设工程中质量、进度和造价目标，应具有相同的优先等级",{"key":23,"text":24,"correct":14},"D","质量、进度和造价目标之间相互制约，应使每一个目标均达到最优","本题考查的是目标控制。选项A错误，应形成“自上而下层层展开、自下而上层层保证”的目标体系；选项C错误，不同建设工程三大目标可具有不同的优先等级；选项D错误，建设工程三大目标之间密切联系、相互制约，需要应用多目标决策、多级梯阶、动态规划等理论统筹考虑、分析论证，努力在“质量优、投资省、工期短”之间寻求最佳匹配。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]