[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103577,780,1,"单选题","（2020年真题）应用建筑信息建模（BIM）技术进行工程造价控制时，需要建立（ ）模型。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","BIM6D",false,{"key":16,"text":17,"correct":18},"B","BIM5D",true,{"key":20,"text":21,"correct":14},"C","BIM4D",{"key":23,"text":24,"correct":14},"D","BIM3D","教材页码P150-153 在工程施工阶段可根据施工组织设计将3D模型加施工进度（4D）模拟实际施工，从而通过确定合理的施工方案指导实际施工，还可以进行5D模拟，实现造价控制。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]