[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103571,780,1,"单选题","为完成施工阶段进度控制任务，项目监理机构需要做的工作是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织进度协调会议，协调有关各方关系",true,{"key":16,"text":17,"correct":18},"B","审查确认施工分包单位资格",false,{"key":20,"text":21,"correct":18},"C","审查施工组织设计",{"key":23,"text":24,"correct":18},"D","严格进行付款控制","考点:目标控制。为完成施工阶段进度控制任务，项目监理机构需要做好以下工作：完善建设工程控制性进度计划；审查施工单位提交的施工进度计划；协助建设单位编制和实施由建设单位负责供应的材料和设备供应进度计划；组织进度协调会议，协调有关各方关系；跟踪检查实际施工进度；研究制定预防工期索赔的措施，做好工程延期审批工作等。选项BC属于施工阶段质量控制的任务，选项D属于施工阶段造价控制的任务。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]