[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103565,780,1,"单选题","下列关于工程建设不同阶段项目监理机构信息收集的表述中，错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工期应收集施工项目管理机构管理程序等信息",false,{"key":16,"text":17,"correct":14},"B","施工招投标阶段应收集工程设计及概算文件等信息",{"key":19,"text":20,"correct":14},"C","设计阶段应收集拟建工程所在地政府部门相关规定等信息",{"key":22,"text":23,"correct":24},"D","施工期应收集与建设工程相关的市场、资源等信息",true,"2020版教材P137-139 本题考查的是信息管理。选项D，属于建设工程决策阶段项目监理机构应收集的信息内容。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]