[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103563":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103563,780,1,"单选题","如果要减少投资、节约费用，势必会考虑降低工程项目的功能要求和质量标准，这表明投资目标与进度目标存在（ ）关系。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","既不对立又不统一",false,{"key":16,"text":17,"correct":14},"B","既对立又统一",{"key":19,"text":20,"correct":21},"C","对立",true,{"key":23,"text":24,"correct":14},"D","统一","2020版教材P131-135 本题考查重点是“建设工程三大目标之间的关系”。 在通常情况下，如果对工程质量有较高的要求，就需要投入较多的资金和花费较长的建设时间;如果要抢时间、争进度，以极短的时间完成建设工程，势必会增加投资或者使工程质量下降;如果要减少投资、节约费用，势必会考虑降低工程项目的功能要求和质量标准。这些表明，建设工程三大目标之间存在着矛盾和对立的一面。因此，本题的正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]