[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103559":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103559,780,1,"单选题","因建设单位原因导致施工合同解除时，项目监理机构应按施工合同约定与建设单位和施工单位协商确定施工单位应得款项，并签发()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","费用索赔报审表",false,{"key":16,"text":17,"correct":14},"B","工程暂停令",{"key":19,"text":20,"correct":21},"C","工程款支付证书",true,{"key":23,"text":24,"correct":14},"D","工程临时或最终延期报审表","2020教材P135-137 因建设单位原因导致施工合同解除时，项目监理机构应按施工合同约定与建设单位和施工单位协商确定施工单位应得款项，并签发工程款支付证书。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]