[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103550,780,1,"单选题","根据《建设工程监理规范》GB／T 50319—2013，施工单位未经批准擅自施工的。总监理工程师应()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","及时签发《监理通知单》",false,{"key":16,"text":17,"correct":14},"B","立即报告建设单位",{"key":19,"text":20,"correct":21},"C","及时签发《工程暂停令》",true,{"key":23,"text":24,"correct":14},"D","立即报告政府主管部门","2020教材P135-137 项目监理机构发现下列情况之一时，总监理工程师应及时签发工程暂停令: (1) 建设单位要求暂停施工且工程需要暂停施工的; (2) 施工单位未经批准擅自施工或拒绝项目监理机构管理的; (3) 施工单位未按审查通过的工程设计文件施工的; (4) 施工单位违反工程建设强制性标准的; (5) 施工存在重大质量、安全事故隐患或发生质量、安全事故的。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]