[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103548,780,1,"单选题","一般情况下，总监理工程师签发工程暂停令，应事先征得()同意。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","施工单位",{"key":23,"text":24,"correct":18},"D","建设行政主管部门","2020教材P135-137 总监理工程师签发工程暂停令，应事先征得建设单位同意，在紧急情况下未能事先报告时，应在事后及时向建设单位作出书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]