[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103542":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103542,780,1,"单选题","下列选项中，适用于选择合理承发包模式和合同计价方式的措施是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":14},"B","技术措施",{"key":19,"text":20,"correct":14},"C","经济措施",{"key":22,"text":23,"correct":24},"D","合同措施",true,"2020教材P131-135 三大目标控制的合同措施：加强合同管理是控制建设工程目标的重要措施。选择合理的承发包模式和合同计价方式，选定满意的施工单位及材料设备供应单位，拟订完善的合同条款，并动态跟踪合同执行情况及处理好工程索赔等，是控制建设工程目标的重要合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]