[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103536,780,1,"单选题","下列选项中，属于建设工程目标控制经济措施的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明确目标控制人员的任务和职能分工",false,{"key":16,"text":17,"correct":14},"B","提出多个不同的技术方案",{"key":19,"text":20,"correct":14},"C","分析不同合同之间的相互联系",{"key":22,"text":23,"correct":24},"D","投资偏差分析",true,"2020教材P131-135 无论是对建设工程造价目标实施控制，还是对建设工程质量、进度目标实施控制，都离不开经济措施。经济措施不仅仅是审核工程量、工程款支付申请及工程结算报告，还需要编制和实施资金使用计划，对工程变更方案进行技术经济分析等。而且通过投资偏差分析和未完工程投资预测，可发现一些可能引起未完工程投资增加的潜在问题，从而便于以主动控制为出发点，采取有效措施加以预防。 A项，属于组织措施； B项，属于技术措施； C项，属于合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]