[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103535":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103535,780,1,"单选题","为了有效控制建设工程质量、造价、进度三大目标，可采取的技术措施是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","审查、论证建设工程施工方案",true,{"key":16,"text":17,"correct":18},"B","动态跟踪建设工程合同执行情况",false,{"key":20,"text":21,"correct":18},"C","建立建设工程目标控制工作考评机制",{"key":23,"text":24,"correct":18},"D","进行建设工程变更方案的技术经济分析","2020教材P131-135 为了对建设工程目标实施有效控制，需要对多个可能的建设方案、施工方案等进行技术可行性分析。为此，需要对各种技术数据进行审核、比较，需要对施工组织设计、施工方案等进行审查、论证等。此外，在整个建设工程实施过程中，还需要采用工程网络计划技术、信息化技术等实施动态控制。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]