[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103503":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103503,780,1,"单选题","根据《建设工程监理规范》（GB\u002FT 50319-2013），施工单位的下列行为中，总监理工程师应及时签发工程暂停令的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","未按专项施工方案施工",false,{"key":16,"text":17,"correct":18},"B","拒绝项目监理机构管理",true,{"key":20,"text":21,"correct":14},"C","未按施工组织设计施工",{"key":23,"text":24,"correct":14},"D","施工存在安全事故隐患","本题考查的是合同管理。项目监理机构发现下列情况之一时，总监理工程师应及时签发工程暂停令：（1）建设单位要求暂停施工且工程需要暂停施工的；（2）施工单位未经批准擅自施工或拒绝项目监理机构管理的；（3）施工单位未按审查通过的工程设计文件施工的；（4）施工单位违反工程建设强制性标准的；（5）施工存在重大质量、安全事故隐患或发生质量、安全事故的。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]