[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103502,780,1,"单选题","在建设工程质量、造价、进度三大目标中，如果要抢时间、争进度，以极短的时间完成建设工程，势必会增加投资或者使工程质量下降，这主要是体现了三大目标之间的（ ）关系。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","对立",true,{"key":16,"text":17,"correct":18},"B","统一",false,{"key":20,"text":21,"correct":18},"C","分解",{"key":23,"text":24,"correct":18},"D","协调","本题考查的是目标控制。三大目标之间的对立关系：在通常情况下，如果对工程质量有较高的要求，就需要投入较多的资金和花费较长的建设时间；如果要抢时间、争进度，以极短的时间完成建设工程，势必会增加投资或者使工程质量下降；如果要减少投资、节约费用，势必会考虑降低工程项目的功能要求和质量标准。这些表明，建设工程三大目标之间存在着矛盾和对立的一面。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]