[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103475":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103475,780,1,"单选题","下列工程造价控制工作中，属于项目监理机构在施工阶段控制工程造价的工作内容是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定期进行工程计量",true,{"key":16,"text":17,"correct":18},"B","审查工程概算",false,{"key":20,"text":21,"correct":18},"C","进行建设方案比选",{"key":23,"text":24,"correct":18},"D","进行投资方案论证","",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]