[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103451":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103451,780,1,"单选题","(2018年真题）关于建设工程监理文件资料管理的说法，正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理文件资料有追溯性要求时，收文登记应注意核查所填内容是否可追溯",true,{"key":16,"text":17,"correct":18},"B","监理文件资料的收文登记人员应确定该文件资料是否要传阅及传阅范围",false,{"key":20,"text":21,"correct":18},"C","监理文件资料完成传阅程序后应按监理单位对项目检查的需要进行分类存放",{"key":23,"text":24,"correct":18},"D","监理文件资料应按施工总承包单位、分包单位和材料供应单位进行分类","本题考查的是管理职责。在监理文件资料有追溯性要求的情况下，应注意核查所填内容是否可追溯。选项B应该是由总监理工程师或其授权的监理工程师确定是否传阅；选项C监理文件资料的分类应根据项目的施工顺序、施工承包体系、单位工程的划分以及工程质量验收程序等；选项D监理文件资料可以按施工单位、专业施工部位、单位工程等进行分类。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]