[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103442":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103442,780,1,"单选题","(2009年真题）下列单位中，不能使用工程变更单的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","建设单位",false,{"key":16,"text":17,"correct":14},"B","监理单位",{"key":19,"text":20,"correct":14},"C","施工单位",{"key":22,"text":23,"correct":24},"D","检测单位",true,"施工单位、建设单位、工程监理单位提出工程变更时，应填写《工程变更单》。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]