[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103428":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103428,780,1,"单选题","不需要建设单位审批同意的表式是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程款支付报审表",false,{"key":16,"text":17,"correct":18},"B","专项施工方案",true,{"key":20,"text":21,"correct":14},"C","费用索赔报审表",{"key":23,"text":24,"correct":14},"D","工程临时或最终延期报审表","2020版教材P154-158 下列表式需要建设单位审批同意: (1) B.0.1 施工组织设计或(专项)施工方案报审表(仅对超过一定规模的危险性较大的分部分项工程专项施工方案) ; (2) B.0.2 工程开工报审表; (3) B.0. 3 工程复工报审表; (4) B.0.11 工程款支付报审表; (5) B.0.13 费用索赔报审表; (6) B.0.14 工程临时或最终延期报审表。 选项B正确。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]