[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103411":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103411,780,1,"单选题","关于建设工程档案编制要求和组卷方法的说法，正确的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","文件资料应采用手写形式并使用档案规定用笔，手工签字",false,{"key":16,"text":17,"correct":14},"B","建设工程由多个单位工程组成时，应按分部工程组卷",{"key":19,"text":20,"correct":21},"C","案卷内不应有重份文件，印刷成册的工程文件应保持原状",true,{"key":23,"text":24,"correct":14},"D","既有文字材料又有图纸的案卷，应将图纸排前，文字材料排后","2020教材P162-168 文件资料应采用打印形式并使用档案规定用笔，手工签字，A选项错。 一个建设工程由多个单位工程组成时，应按单位工程组卷，B选项错。 案卷内不应有重份文件，印刷成册的工程文件应保持原状。C选项正确。 既有文字材料又有图纸的案卷，文字材料排前，图纸排后。D选项错。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]