[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103408":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103408,780,1,"单选题","下列表式中，必须由项目经理签字并加盖施工单位公章的是( )。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程开工令",false,{"key":16,"text":17,"correct":14},"B","施工进度计划报审表",{"key":19,"text":20,"correct":14},"C","分包单位资格报审表",{"key":22,"text":23,"correct":24},"D","单位工程竣工验收报审表",true,"2020教材P154-158 需要由施工项目经理签字并加盖施工单位公章的表式：工程开工报审表、单位工程竣工验收报审表。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]