[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103365,780,1,"单选题","根据《建设工程监理规范》，下列表式中，不需要总监理工程师加盖执业印章，但需要建设单位盖章的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工组织设计报审表",false,{"key":16,"text":17,"correct":14},"B","专项施工方案报审表",{"key":19,"text":20,"correct":14},"C","工程开工报审表",{"key":22,"text":23,"correct":24},"D","工程复工报审表",true,"⒊需要建设单位审批同意的表式 ⑴B.0.1 施工组织设计或(专项)施工方案报审表(仅对超过一定规模的危险性较大的分部分项工程专项施工方案)； ⑵B.0.2 工程开工报审表； ⑶B.0.3 工程复工报审表； ⑷B.0.11 工程款支付报审表 ⑸B.0.13 费用索赔报审表； ⑹B.0.14 工程临时或最终延期报审表。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]