[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103344":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103344,780,1,"单选题","(2015年真题）常用的风险分析与评价方法不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划评审技术法",false,{"key":16,"text":17,"correct":14},"B","蒙特卡洛模拟法",{"key":19,"text":20,"correct":14},"C","调查打分法",{"key":22,"text":23,"correct":24},"D","头脑风暴法",true,"头脑风暴法属于风险识别方法中的专家调查法。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]