[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103339":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103339,780,1,"单选题","(2011年真题）在损失控制计划系统中，使因严重风险事件而中断的工程实施过程尽快全面恢复，并减少进一步的损失的计划是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","应急计划",true,{"key":16,"text":17,"correct":18},"B","恢复计划",false,{"key":20,"text":21,"correct":18},"C","灾难计划",{"key":23,"text":24,"correct":18},"D","预防计划","本题考核损失控制计划的概念。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]