[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103336":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103336,780,1,"单选题","(2010年真题）下列确认工程建设最终风险清单的风险识别方法组合中，正确的组合是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","专家调查法和初始清单法",false,{"key":16,"text":17,"correct":14},"B","专家调查法和经验数据法",{"key":19,"text":20,"correct":14},"C","初始清单法和经验数据法",{"key":22,"text":23,"correct":24},"D","初始清单法和风险调查法",true,"风险调查可以从组织、技术、自然环境、经济、合同等方面分析拟建工程的特点以及相应的潜在风险。即在初始清单的基础上进行风险调查",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]