[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103332":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103332,780,1,"单选题","(2015年真题）下列计划中，属于应急计划的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","现场人员安全撤离计划",false,{"key":16,"text":17,"correct":18},"B","材料与设备采购调整计划",true,{"key":20,"text":21,"correct":14},"C","伤亡人员援救及处理计划",{"key":23,"text":24,"correct":14},"D","资产和环境损害控制计划","应急计划应包括的内容有： （1）调整整个建设工程实施进度计划、材料与设备的采购计划、供应计划； （2）全面审查可使用的资金情况； （3）准备保险索赔依据； （4）确定保险索赔的额度； （5）起草保险索赔报告； （6）必要时需调整筹资计划",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]