[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103311,780,1,"单选题","下列选项中，工程设计进度计划的审查内容不包括()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计划中各个节点是否存在漏项",false,{"key":16,"text":17,"correct":18},"B","工程监理单位应审查设计单位提交的设计成果，并提出评估报告",true,{"key":20,"text":21,"correct":14},"C","出图节点是否符合建设工程总体计划进度节点要求",{"key":23,"text":24,"correct":14},"D","分析各阶段、各专业工种设计工作量和工作难度，并审查相应设计人员的配置安排是否合理","2020版教材P180-184 本题考查的是勘察设计阶段服务内容。工程设计进度计划的审查内容包括：(1)计划中各个节点是否存在漏项；(2)出图节点是否符合建设工程总体计划进度节点要求；(3)分析各阶段、各专业工种设计工作量和工作难度，并审查相应设计人员的配置安排是否合理；(4)各专业计划的衔接是否合理，是否满足工程需要。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]