[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103296":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103296,780,1,"单选题","对于建设工程风险来说，工程保险是建设工程风险中采用的()对策。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","风险转移",true,{"key":16,"text":17,"correct":18},"B","非保险转移",false,{"key":20,"text":21,"correct":18},"C","损失控制",{"key":23,"text":24,"correct":18},"D","风险回避","2020版教材P171-180 本题考查的是建设工程风险管理。风险转移可分为非保险转移和保险转移两大类。保险转移通常直接称为工程保险。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]