[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1103287,780,1,"单选题","下列选项中，不属于在决定进行风险控制时，应该制定的计划是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","预防计划",false,{"key":16,"text":17,"correct":14},"B","灾难计划",{"key":19,"text":20,"correct":14},"C","应急计划",{"key":22,"text":23,"correct":24},"D","报警计划",true,"2020版教材P171-180 本题考查的是建设工程风险管理。损失控制计划系统一般应由预防计划、灾难计划和应急计划三部分组成。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]