[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103211":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103211,780,1,"单选题","之所以说CM模式介入工程的时间较早，是因为CM单位一般在项目()阶段介入。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","设计",true,{"key":16,"text":17,"correct":18},"B","立项",false,{"key":20,"text":21,"correct":18},"C","招投标",{"key":23,"text":24,"correct":18},"D","可行性研究","2020版教材P194-197 非代理型CM模式，由于CM单位介入工程时间较早，一般在设计阶段介入，且不承担设计任务。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]