[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103205":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1103205,780,1,"单选题","Project Controlling咨询单位的核心工作是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","信息处理",true,{"key":16,"text":17,"correct":18},"B","收集信息",false,{"key":20,"text":21,"correct":18},"C","分析信息",{"key":23,"text":24,"correct":18},"D","出具有关的书面报告","2020版教材P201-205 本题考查的是2020版教材Project Controlling模式。2020版教材Project Controlling咨询单位的核心工作是信息处理，即收集信息、分析信息、出具有关的书面报告。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]