[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103140":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1103140,780,1,"单选题","（2020年真题）根据《建筑法》，工程监理人员发现工程设计不符合建筑工程质量标准时，正确的做法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接通知设计单位改正",false,{"key":16,"text":17,"correct":18},"B","报告建设单位要求设计单位改正",true,{"key":20,"text":21,"correct":14},"C","根据质量标准直接修改设计",{"key":23,"text":24,"correct":14},"D","要求施工单位修改设计后实施","教材页码P3-6 根据《建筑法》第三十二条内容，工程监理人员发现工程设计不符合建筑工程质量标准或者合同约定的质量要求的，应当报告建设单位要求设计单位改正。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]