[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103099":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103099,780,1,"单选题","在建设工程勘察设计工作中，对于重大工程和技术复杂工程，可根据需要增加（ ）阶段。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","详细勘察",false,{"key":16,"text":17,"correct":14},"B","方案设计",{"key":19,"text":20,"correct":21},"C","技术设计",true,{"key":23,"text":24,"correct":14},"D","施工图审查","工程设计：两阶段设计包含初步设计和施工图设计；三阶段设计增加技术设计",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]