[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1103028":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1103028,780,1,"单选题","对于重大工程和技术复杂工程，应根据初步设计和更详细的调查研究资料编制（ ），以进一步解决初步设计中的重大技术问题，使工程设计更具体、更完善，技术指标更好。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","详细勘察计划",false,{"key":16,"text":17,"correct":14},"B","方案设计",{"key":19,"text":20,"correct":21},"C","技术设计",true,{"key":23,"text":24,"correct":14},"D","施工图设计","考点:建设实施阶段的工作内容。工程设计工作一般划分为两个阶段，即初步设计和施工图设计。重大工程和技术复杂工程，可根据需要增加技术设计阶段。技术设计应根据初步设计和更详细的调查研究资料编制，以进一步解决初步设计中的重大技术问题，如：工艺流程、建筑结构、设备选型及数量确定等，使工程设计更具体、更完善，技术指标更好。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]