[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1102985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1102985,780,1,"单选题","某施工项目招标，招标文件开始出售的时间为3月20日，停止出售的时间为3月30日，提交投标文件的截止时间为4月25日，评标结束的时间为4月30日，则投标有效期开始的时间为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3月20日",false,{"key":16,"text":17,"correct":14},"B","3月30日",{"key":19,"text":20,"correct":21},"C","4月25日",true,{"key":23,"text":24,"correct":14},"D","4月30日","\\考点:《招标投标法实施条例》相关内容。投标有效期从提交投标文件的截止之日起算。",{"id":6,"name":27,"category":28,"favorite":29},"监理概论","建筑工程",0]